2020 Street Program Information-Phase 2

The Village of Chicago Ridge will begin Phase 2 of the 2020 Street Program at the beginning of August.


Project: Parkside Ave., Major Ave., and 106th Street Roadway Improvements

 

Contractor: Lindahl Bros.

 

Resident Engineer: Paul Feeney (Christopher B. Burke Engineering, Ltd.)

 

Anticipated Start Date: August 10, 2020

 

Project Duration: 35 working days from Notice to Proceed, or roughly late September completion

 

Project Locations: Parkside Avenue (107th Street to 105th Street)

                                Major Avenue (106th Street to 105th Street)

                               106th Street (Major Avenue to Parkside Avenue)

Facebook Twitter Email

Other News in Chicago Ridge News

Backflow Testing Compliance Issues

Posted on: September 24, 2020

ComEd COVID-19Related Energy Scams

Posted on: September 21, 2020

Grant Available for Small Businesses

Posted on: September 21, 2020

An Update from the Mayor

Posted on: September 1, 2020

Nicor Gas Energy Assistance

Posted on: August 24, 2020

2020 Street Program Information

Posted on: July 13, 2020

Stay home! Pay Taxes Online!

Posted on: July 13, 2020

A Message from the Mayor-UPDATED

Posted on: June 2, 2020

Get Counted In Illinois

Posted on: February 25, 2020