News Flash

Chicago Ridge News

Posted on: July 28, 2020

2020 Street Program Information-Phase 2

The Village of Chicago Ridge will begin Phase 2 of the 2020 Street Program at the beginning of August.


Project: Parkside Ave., Major Ave., and 106th Street Roadway Improvements

 

Contractor: Lindahl Bros.

 

Resident Engineer: Paul Feeney (Christopher B. Burke Engineering, Ltd.)

 

Anticipated Start Date: August 10, 2020

 

Project Duration: 35 working days from Notice to Proceed, or roughly late September completion

 

Project Locations: Parkside Avenue (107th Street to 105th Street)

                                Major Avenue (106th Street to 105th Street)

                               106th Street (Major Avenue to Parkside Avenue)